The Project of Three Semi-Detached Houses in Nhon Trach, Dong Nai

Description
The project includes 03 semi-detached houses in Long Phuoc Commune, Nhon Trach District, Dong Nai Province. Total installed capacity 18.24kW, annual electricity output 26,630kWh, bringing investment efficiency about 20%/year
Project Details
  • Customers: S190251DTT
  • Project Location: Nhơn Trạch,Đồng Nai
  • Execution time: 12/2019
  • Cost: ~400 triệu

The project includes 03 semi-detached houses in Long Phuoc Commune, Nhon Trach District, Dong Nai Province. Total installed capacity 18.24kW, annual electricity output 26,630kWh, bringing investment efficiency about 20%/year.

CURRENT STATUS INFORMATION:

- Direction: southwest

 - Roof inclination: 6 degrees

- Installation on corrugated iron roofsheets

- Shading: the surroundings are not shaded